BUILDER DELAY INDEX · INDIA

Which builders push possession back?

Every builder with at least 5 registered projects whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.

38,515projects past their original possession date
33%had the date pushed back
8.9 moaverage delay per project

Most delayed

BuilderAvg delayPushed backProjects dueRuko
1Futureworld Greenhomes Pvt. Ltd. · Uttar Pradesh84.1 mo100% of 7772Swastik Realty PVT LTD · Maharashtra63 mo80% of 5553Mahavir Homes · Maharashtra60.8 mo80% of 5554Spenta Enclave Private Limited · Maharashtra58.5 mo100% of 6665Luxora Infrastructure Private Limited · Maharashtra55.7 mo80% of 2020206Strawberry Constructions Pvt. Ltd. · Maharashtra48.6 mo100% of 5557Parsn Construction And Developers Private Limited · Maharashtra48.4 mo100% of 5548Ekta Parksville Homes Pvt. Ltd. · Maharashtra48.1 mo100% of 7779D S Developers · Maharashtra48 mo80% of 55510Viva Homes Private Limited · Maharashtra47.8 mo83% of 12121211Amit Enterprises Housing Limited · Maharashtra47.5 mo83% of 66612Maverick Realtors · Maharashtra47.1 mo89% of 99913Jaypee Infratech Limited · Uttar Pradesh46.8 mo67% of 18181214Synergy Properties · Maharashtra46.2 mo89% of 99715Nirmal Lifestyle LTD · Maharashtra45.8 mo80% of 55516Shah Group Builders LTD · Maharashtra45.6 mo80% of 55517Madhu Harshad Doshi · Maharashtra45.4 mo100% of 77718Bhumiraj Builders Pvt. Ltd. · Maharashtra44.2 mo80% of 55519Jaykali Developers Private Limited · Maharashtra43.3 mo83% of 66620Pankaj Developers · Maharashtra42.8 mo80% of 55521Sanklecha Construction Private Limited · Maharashtra41.7 mo85% of 13131322Sudhanshu Infrastructures PVT LTD · Maharashtra39.6 mo100% of 55523Shreenath Enterprises · Maharashtra37.9 mo86% of 77524Hiranimanthan Builders And Developers · Maharashtra37.7 mo67% of 66525Lucina Land Development Limited · Maharashtra37.2 mo67% of 99926Bhalchandra Wadnerkar · Maharashtra36.8 mo38% of 88827Bhagvati Infra · Maharashtra36 mo33% of 66628Shantee Homes Realty LLP · Maharashtra33.8 mo50% of 66629Wadhwa Buildcon LLP · Maharashtra32.8 mo60% of 55530Maheshwari Developers · Maharashtra32.6 mo60% of 55431Shiv Sai Developers · Maharashtra32.2 mo67% of 66632Ravi Developments · Maharashtra31.9 mo64% of 11111133Navkar Infra Projects · Maharashtra31.4 mo80% of 55534Chirag Developers · Maharashtra31.4 mo63% of 88835Viva Winner Venture Relators LLP · Maharashtra31.3 mo100% of 66636Selene Estate LTD · Tamil Nadu31.2 mo80% of 55237Prathmesh Developers · Maharashtra31.2 mo100% of 55338Pune Projects LLP · Maharashtra31.2 mo100% of 66339Classic Promoters And Builders Private Limited · Maharashtra30.5 mo88% of 16161440Rajheramb Properties · Maharashtra30.3 mo100% of 66641Siddharth Properties · Maharashtra29.8 mo80% of 1010942Nirmal Lifestyle (kalyan) Private Limited · Maharashtra29.6 mo82% of 28282843Pratham Developers · Maharashtra28.7 mo83% of 66544Prasanna Developers · Maharashtra28.6 mo100% of 55345Sheth Developers · Maharashtra27.9 mo83% of 12121146Ekdanta Nest LLP · Maharashtra27.6 mo60% of 55447Heritage Lifestyles & Developers Pvt. Ltd. · Maharashtra27 mo100% of 77648Avior Shelters LLP · Maharashtra26.7 mo67% of 66649Godrej Skyline Developers Limited · Maharashtra26.6 mo86% of 77550Adhiraj Constructions Private Limited · Maharashtra26.2 mo70% of 101010

Least delayed

Builders with no lapsed registration and at most a quarter of projects at Ruko.

How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.