BUILDER DELAY INDEX · UTTAR PRADESH

Which builders push possession back?

Every builder with at least 5 registered projects whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.

1,114projects past their original possession date
64%had the date pushed back
13 moaverage delay per project

Most delayed

BuilderAvg delayPushed backProjects dueRuko
1Futureworld Greenhomes Pvt. Ltd.84.1 mo100% of 7772Jaypee Infratech Limited46.8 mo67% of 1818123Max-digi Infotech Private Limited20.8 mo80% of 5544Scc Builders Pvt. Ltd.19.8 mo80% of 5535Panchsheel Buildtech Pvt. Ltd.19 mo67% of 1818116Blue Square Infrastructure LLP16.8 mo100% of 5547Vibhor Vaibhav Infrahome Pvt. Ltd.15.6 mo40% of 5528Ivr Prime Developers (avadi) Private Limited15.5 mo100% of 6669Ajnara Realtech Limited15.2 mo50% of 66610Ar Landcraft LLP15 mo100% of 66611Ajnara India Limited13.6 mo92% of 12121212Mr Proview Realtech Private Limited9.1 mo56% of 99413Uppal Chadha Hi-tech Developers Pvt. Ltd.8.6 mo54% of 26261314High End Infratech Private Limited8.4 mo100% of 55115U.p. Awas Evam Vikas Parishad8.3 mo36% of 1111416Parsvnath Developers Limited8.1 mo63% of 88817Yamuna Expressway Industrial Devlopment Authority7.2 mo60% of 1010518Iitl-nimbus The Express Park View7.2 mo60% of 55219Cbs International Projects Private Limited7.2 mo100% of 55220Adani Infrastructure Integrated Solutions Limited (formerly Known As Jaiprakash Associates Limited)6.7 mo56% of 39393921Gardenia Aims Developers Private Limited6 mo100% of 77122Contend Infrastructure Private Limited ( Antriksh6 mo100% of 66223Rise Projects PVT Ltdeuphoria Sports City Private Limited6 mo60% of 55224Wtc Noida Development Company PVT LTD6 mo100% of 55525Supertech Limited5.7 mo72% of 25252526Logix Infratech Private Limited5.6 mo100% of 55527M/S Uttam Steels & Associates { Consortium) Througansal Hi-tech Townships LTD5.3 mo89% of 18181428Gaursons Realtech Private Limited5.1 mo50% of 1010429Rajesh Projects (india) Pvt. LTD4.5 mo75% of 88830Unitech Limited (mr.ramesh Chandra, Mr.ajay Chandra,mr.sanjay Chandra)3.8 mo63% of 88331Agarwal Associates (promoters) Limited3.6 mo60% of 55132Imperia Structures LTD3.6 mo60% of 55233Ghaziabad Development Authority1.8 mo25% of 2424234Smv Agencies PVT LTD1.2 mo20% of 55135Greater Noida Industrial Development Authority0.8 mo10% of 1010136Aims Max Gardenia Developers Private Limited0.8 mo13% of 881

Least delayed

Builders with no lapsed registration and at most a quarter of projects at Ruko.

BuilderAvg delayPushed backProjects dueRuko

How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.