BUILDER DELAY INDEX · GAUTAM BUDDHA NAGAR
Which builders push possession back?
Every builder with at least 5 registered projects in Gautam Buddha Nagar whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.
753projects past their original possession date
68%had the date pushed back
14 moaverage delay per project
Most delayed
BuilderAvg delayPushed backProjects dueRuko
1Futureworld Greenhomes Pvt. Ltd.84.1 mo100% of 7772Jaypee Infratech Limited46.8 mo67% of 1818123Max-digi Infotech Private Limited20.8 mo80% of 5544Blue Square Infrastructure LLP16.8 mo100% of 5545Panchsheel Buildtech Pvt. Ltd.16 mo58% of 121266Ivr Prime Developers (avadi) Private Limited15.5 mo100% of 6667Ajnara Realtech Limited15.2 mo50% of 6668Ar Landcraft LLP15 mo100% of 6669Parsvnath Developers Limited10.8 mo83% of 66610Ajnara India Limited9.5 mo88% of 88811Yamuna Expressway Industrial Devlopment Authority7.2 mo60% of 1010512Iitl-nimbus The Express Park View7.2 mo60% of 55213Cbs International Projects Private Limited7.2 mo100% of 55214Adani Infrastructure Integrated Solutions Limited (formerly Known As Jaiprakash Associates Limited)6.7 mo56% of 39393915Gardenia Aims Developers Private Limited6 mo100% of 77116Contend Infrastructure Private Limited ( Antriksh6 mo100% of 66217Wtc Noida Development Company PVT LTD6 mo100% of 55518Rise Projects PVT Ltdeuphoria Sports City Private Limited6 mo60% of 55219Supertech Limited5.7 mo72% of 25252520Logix Infratech Private Limited5.6 mo100% of 55521M/S Uttam Steels & Associates { Consortium) Througansal Hi-tech Townships LTD5.3 mo89% of 18181422Gaursons Realtech Private Limited5.1 mo50% of 1010423Rajesh Projects (india) Pvt. LTD4.5 mo75% of 88824Unitech Limited (mr.ramesh Chandra, Mr.ajay Chandra,mr.sanjay Chandra)3.8 mo63% of 88325Imperia Structures LTD3.6 mo60% of 55226Greater Noida Industrial Development Authority0.8 mo10% of 1010127Aims Max Gardenia Developers Private Limited0.8 mo13% of 881Least delayed
Builders with no lapsed registration and at most a quarter of projects at Ruko.
BuilderAvg delayPushed backProjects dueRuko
How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.