BUILDER

Synergy Properties

Type Firm / individualRERA projects 10Districts Pune
BUILDER THOK
Ruko
8 of 10projects with possession moved
52 moaverage extension when late
1lapsed registrations
10MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2021Dec 2028
84 mo
Dec 2021Apr 2032
124 mo
Dec 2021Dec 2031
120 mo
Paloma
Adhale Bk
Aug 2023Aug 2023
not moved
Jun 2025Apr 2027
22 mo
Jun 2025Oct 2027
28 mo
Satvam Hills A5
Mulshi · lapsed
Jun 2025Feb 2026
8 mo
Sept 2025Apr 2027
19 mo
Jan 2026Dec 2026
11 mo
Aug 2029Aug 2029
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Casuarina - Cluster C And D
P52100010452 · Male
Ruko
Bougain Villa - Cluster 1
P52100011902 · Pasure
Ruko
Bougain Villa - Cluster 3
P52100009058 · Pasure
Ruko
Paloma
P52100028735 · Adhale Bk
Ruko
Satvam Hills A4
P52100052106 · Mulshi
Ruko
Satvam Hills A6
P52100054456 · Mulshi
Ruko
Satvam Hills A5
P52100052048 · Mulshi
Ruko
Paloma - Eva
P52100054156 · Mawal
Dhyaan Do
Paloma Azure
P52100078832 · Mawal
Dhyaan Do
Satvam Hills C5
PP1260002601969 · Mulshi
Pakka