BUILDER DELAY INDEX · THANE
Which builders push possession back?
Every builder with at least 5 registered projects in Thane whose original possession date has already passed, ranked by how many months that date moved on the official RERA record.
By cityPuneThaneMumbai SuburbanRaigarhNashikPalgharNagpurMumbai CityAurangabadRatnagiriSataraSangliKolhapurSolapurAhmednagarAmravatiSindhudurgWardhaJalgaonChandrapur
4,436projects past their original possession date
37%had the date pushed back
9.7 moaverage delay per project
Most delayed
BuilderAvg delayPushed backProjects dueRuko
1Bhalchandra Wadnerkar58.8 mo60% of 5552Strawberry Constructions Pvt. Ltd.48.6 mo100% of 5553Madhu Harshad Doshi45.4 mo100% of 7764Bhumiraj Builders Pvt. Ltd.44.2 mo80% of 5555Jaykali Developers Private Limited43.3 mo83% of 6656Wadhwa Buildcon LLP32.8 mo60% of 5557Ravi Developments31.9 mo64% of 1111118Sanghvi Premises Private Limited30.6 mo80% of 5549Nirmal Lifestyle (kalyan) Private Limited29.6 mo82% of 28282610Sheth Developers26.7 mo67% of 66511Siddhi Real Estate Developers25 mo80% of 55312Bhavani Enterprises22 mo67% of 66413M K Patil Developers18.8 mo60% of 55514Shree Khidkaleshwar Property Developers Pvt. Ltd.18 mo100% of 55315Gopal Krishna Developers17.6 mo60% of 55416Lodha Developers Limited17.2 mo65% of 2323917Arihant Enterprises16.9 mo50% of 1010818Yash Infra15.7 mo43% of 77619Charms Developers13.2 mo40% of 55520Mohan Lifespaces LLP12.4 mo50% of 18181421Matrix Enclaves Projects Dev. Pvt. LTD12 mo80% of 55322Lfka Builders And Developers11.6 mo40% of 55523Karrm Infrastructure Private Limited11.6 mo60% of 55524Sagar Enterprise11.3 mo50% of 66525Sai Developers11.2 mo20% of 55526Ishwar Reality10.8 mo50% of 66527Shree Developers10.8 mo38% of 88828Siddhi Krish Developers10.7 mo17% of 66629Runwal Residency Private Limited10.6 mo67% of 1515530Siddhivinayak Developers10.4 mo29% of 77631Omkar Enterprises10.2 mo33% of 99932Om Sai Developers9.6 mo20% of 55533Acme Housing India Private Limited9.6 mo57% of 77634Hubtown Limited9.3 mo67% of 66435Pramukh Developers9.2 mo60% of 55436Panvelkar Infrastructures Private Limited9 mo67% of 66537Rna Builders (ng)8.3 mo29% of 14141138Unnathi Estates8 mo33% of 66439Shreeji Developers6.4 mo43% of 77540Anil Hardasmal Tharwani6.4 mo30% of 1010941Vikas Harakchand Jain6.4 mo40% of 55242Anjana Sahebrao Chavan5.8 mo40% of 55443Royale Urbanspace LLP5.7 mo29% of 77644Mohan Hardasmal Tharwani5.7 mo42% of 1212845Telange Builders & Developers Private Limited5.6 mo40% of 55446Neptune Developers Limited5 mo41% of 41412347Aditya Associates4.9 mo22% of 99848Shree Sai Developers4.8 mo20% of 55549Unnathi Associates4.4 mo40% of 55150Gayasuddin Riyazuddin Khan4.4 mo20% of 555Least delayed
Builders with no lapsed registration and at most a quarter of projects at Ruko.
BuilderAvg delayPushed backProjects dueRuko
1Agile Real Estate Pvt. Ltd.0 mo0% of 131312Raymond Limited0 mo0% of 9923Jp Infra Realty Private Limited0 mo0% of 770How it's measured: for each project, months between the possession date first declared to the regulator and the latest one (zero if unchanged), averaged per builder. Only records we have verified against the regulator count; cancelled and withdrawn registrations are excluded. A delay on the record is not by itself a finding of fault. See the methodology.