Sanklecha Construction Private Limited

Type CompanyRERA projects 13Districts Nashik, Ahmednagar
BUILDER THOK
Ruko
7 of 8projects with possession moved
49 moaverage extension when late
0lapsed registrations
13MahaRERA projects · 5 being verified

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
The Metrozone Aspen C1
Nashik (M Corp.)
Mar 2018Sept 2018
6 mo
The Metrozone Athens A1
Nashik (M Corp.)
Mar 2018Sept 2018
6 mo
The Metrozone Aspen C2
Nashik (M Corp.)
Jun 2018Jun 2018
on time
The Metrozone Athens A2
Nashik (M Corp.)
Sept 2018Oct 2022
49 mo
Sept 2018Dec 2023
63 mo
The Metrozone Athens A3
Nashik (M Corp.)
Sept 2018Mar 2021
30 mo
Dec 2019Apr 2028
100 mo
Waterways
Nashik (M Corp.)
Jun 2021Dec 2028
90 mo
——
—
The Metrozone Aspen C3
Nashik (M Corp.)
——
—
——
—
Ganesh Pride
Ahmadnagar (M Corp.)
——
—
——
—

Signals from filings & records

Verification in progressMahaRERA

8 of 13 projects verified against the live MahaRERA record so far. Stats above use verified projects only.

Thok Bajaake crawler
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

The Metrozone Aspen C1
P51600005208 · Nashik (M Corp.)
Ruko
The Metrozone Athens A1
P51600005033 · Nashik (M Corp.)
Ruko
The Metrozone Aspen C2
P51600009327 · Nashik (M Corp.)
Ruko
The Metrozone Athens A2
P51600005464 · Nashik (M Corp.)
Ruko
The Metrozone Hampston B3
P51600012165 · Nashik (M Corp.)
Ruko
The Metrozone Athens A3
P51600009518 · Nashik (M Corp.)
Ruko
The Metrozone Kingston D2
P51600005490 · Nashik (M Corp.)
Ruko
Waterways
P51600008638 · Nashik (M Corp.)
Ruko
The Metrozone Hampston B2
P51600008309 · Nashik (M Corp.)
Not scored
The Metrozone Aspen C3
P51600007130 · Nashik (M Corp.)
Not scored
The Metrozone Kingstone D1
P51600005201 · Nashik (M Corp.)
Not scored
Ganesh Pride
P52200046160 · Ahmadnagar (M Corp.)
Not scored