RERA projects in Gautam Buddha Nagar

Before you book in Gautam Buddha Nagar, see how builders here have kept their possession dates, from public UP RERA and IBBI records.

1,038UP RERA projects · 100% verified so far
54%of projects with both dates on record had possession pushed back (avg 20 months)
179projects flagged “QPR not Uploaded” by the regulator
712projects with UP RERA complaints filed (28,086 complaints; filed, not upheld)
Verdicts so far1,117 scored
Pakka 231 · Dhyaan Do 306 · Ruko 580

Most active builders

All projects in Gautam Buddha Nagar

Neotown Phase-3
UPRERAPRJ7327 · · Patel Advance Jv
POSSESSIONApr 2024COMPLAINTS11SCORE39
Ruko
Neoworld ( Phase-1 Tower-d, E &F)
UPRERAPRJ4124 · · Logix Infra Developers Pvt.ltd.
POSSESSIONJun 2021COMPLAINTS29SCORE44
Ruko
Neoworld ( Phase-2 Tower- A , B & G)
UPRERAPRJ4612 · · Logix Infra Developers Pvt.ltd.
POSSESSION—COMPLAINTS—SCORE49
Ruko
Neoworld ( Phase-3 Tower- C,h, Shops, & Club)
UPRERAPRJ4678 · · Logix Infra Developers Pvt.ltd.
POSSESSION—COMPLAINTS—SCORE49
Ruko
Nilay Square
UPRERAPRJ243992 · Plot No. Slc-3/1, Sector Alpha -II , Greater Noida , Gautam Buddha Nagar, Pin-201310 · Nilay Infratech Private Limited
POSSESSIONJan 2030COMPLAINTS0SCORE93
Pakka
Nimbus The Palm Village
UPRERAPRJ558356 · Plot NO. Gh-03, Sector 22A, Yamuna Expressway Industrial Development Area, District Gautambudh Nagar, Uttar Pradesh. · Iitl- Nimbus The Palm Village
POSSESSIONMar 2028COMPLAINTS0SCORE97
Pakka
Nirala - Biz Park
UPRERAPRJ394364 · · Nirala Infratech Private Limited
POSSESSIONMay 2025COMPLAINTS0SCORE65
Dhyaan Do
Nirala Aspire Ph-iv (B11, B15 To B23)
UPRERAPRJ508551 · Dadri · Iresh Nirala Gold Projects Llpnirala Housing Private Limited
POSSESSIONDec 2024COMPLAINTS2SCORE74
Dhyaan Do
Nirala Aspire PH1 (A1 To A8 & D1 To D5)
UPRERAPRJ4730 · · Nirala Housing Private Limited
POSSESSIONSept 2018COMPLAINTS12SCORE61
Dhyaan Do
Nirala Aspire Phase-ii (B1 To B10, B12 , B14)
UPRERAPRJ783018 · 311 · G3 Aspire Nirala Gold Llpnirala Housing Private Limited
POSSESSIONFeb 2025COMPLAINTS2SCORE74
Dhyaan Do
Nirala Diadem
UPRERAPRJ825497 · Plot No C-6, Sector-10, Greater Noida · Parth Builtech Private Limited
POSSESSIONOct 2030COMPLAINTS1SCORE92
Pakka
Nirala Estate Phase-ii
UPRERAPRJ519100 · · Nirala Infratech Private Limited
POSSESSIONMay 2025COMPLAINTS4SCORE57
Dhyaan Do
Nirala Estate Phase-iii
UPRERAPRJ265789 · · Nirala Infratech Private Limited
POSSESSIONDec 2026COMPLAINTS0SCORE93
Pakka
Nirala Estate Phase-iv
UPRERAPRJ617209 · · Nirala Infratech Private Limited
POSSESSIONDec 2026COMPLAINTS0SCORE93
Pakka
Nirala Estate Phase-v
UPRERAPRJ788191 · · Nirala Infratech Private Limited
POSSESSIONNov 2027COMPLAINTS1SCORE92
Pakka
Nirala Gateway
UPRERAPRJ531916 · Plot No. C-7 · Parth Builtech Private Limited
POSSESSIONApr 2030COMPLAINTS1SCORE92
Pakka
Nirala Greenshire Ph-1 (G6-g12, G14)
UPRERAPRJ4975 · · Nirala Projects Private Limited
POSSESSIONMar 2022COMPLAINTS13SCORE24
Ruko
Nirala Greenshire Ph-ii
UPRERAPRJ120088 · Dadri · Nirala Projects Private Limited
POSSESSIONDec 2027COMPLAINTS0SCORE87
Pakka
Nirala Trio
UPRERAPRJ707952 · Dadri · Nirala World Residency Private Limited
POSSESSIONDec 2028COMPLAINTS0SCORE93
Pakka
Nobility
UPRERAPRJ284035 · Dadri · Homekraft Infra Private Limitedvtech Buildcon Pvt. Ltd.
POSSESSIONJan 2027COMPLAINTS4SCORE72
Dhyaan Do
Noida Cyber Hub
UPRERAPRJ335841 · · Noida Cyber Park Pvt. Ltd.
POSSESSIONMay 2026COMPLAINTS17SCORE40
Ruko
Noida One --Tower A (Phase II)
UPRERAPRJ3841 · · Pioneer Eserve Private Limited
POSSESSIONDec 2020COMPLAINTS2SCORE38
Ruko
Noida World One - Phase 1
UPRERAPRJ7184 · · Cbs International Projects Private Limited
POSSESSIONNov 2020COMPLAINTS11SCORE35
Ruko
Noida World One - Phase 2
UPRERAPRJ7380 · · Cbs International Projects Private Limited
POSSESSIONNov 2020COMPLAINTS2SCORE49
Ruko