RERA projects in Palghar

Before you book in Palghar, see how builders here have kept their possession dates, from public MahaRERA and IBBI records.

2,686MahaRERA projects · 100% verified so far
64%of projects with both dates on record had possession pushed back (avg 19 months)
383lapsed registrations
329projects with MahaRERA complaints filed (1,348 complaints; filed, not upheld)
Verdicts so far2,686 scored
Pakka 1644 · Dhyaan Do 251 · Ruko 791