Ruko
4 of 12projects with possession moved
23 moaverage extension when late
1lapsed registrations
12MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Yash Complex
Pen (M Cl)
Dec 2018Dec 2018
not moved
Mar 2019Mar 2019
not moved
Jun 2019Jun 2019
not moved
Jai Ganesh Residency C Wing
Pimpri Chinchawad (M Corp.)
Jan 2021Jan 2021
not moved
Yash Paradise
Sangameshwar
Apr 2022Dec 2027
68 mo
Surashree
Ambarnath
Dec 2022Dec 2022
not moved
Dec 2024Dec 2024
not moved
Yashasvi Apartment
Baramati · lapsed
Jun 2025Jun 2025
lapsed
Oct 2025Feb 2027
16 mo
Dec 2026Dec 2026
not moved
Yash Avenida
Pune (M Corp.)
Dec 2027Apr 2028
4 mo
Dec 2029Apr 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Yash Complex
P52000010152 · Pen (M Cl)
Ruko
Giri Heaven
P51700018436 · Thane
Ruko
Yash Heights
P52000007304 · Ulawe
Ruko
Jai Ganesh Residency C Wing
P52100005820 · Pimpri Chinchawad (M Corp.)
Pakka
Yash Paradise
P52800022568 · Sangameshwar
Ruko
Surashree
P51700016592 · Ambarnath
Ruko
Raj Laxmi Residency
P51600033936 · Nashik
Ruko
Yashasvi Apartment
P52100028588 · Baramati
Ruko
Galaxy Co-operative Housing Society LTD
P52100054738 · Haveli
Dhyaan Do
Shree Radhe Shyam Residency
P51600078234 · Nashik
Pakka
Yash Avenida
P52100047510 · Pune (M Corp.)
Pakka
Reyaansh Arcade
P51700077201 · Ambarnath
Pakka