BUILDER

Vinayaka Realtors And Developers

Type Firm / individualRERA projects 4Districts Mumbai Suburban
BUILDER THOK
Ruko
3 of 4projects with possession moved
21 moaverage extension when late
2lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2019Dec 2021
24 mo
Nandadeep Residency
Kurla · lapsed
Nov 2022Nov 2023
12 mo
Dec 2023Mar 2026
27 mo
Simra Residency
Kurla · lapsed
Dec 2024Dec 2024
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Solomon Residency
P51800010650 · Kurla
Ruko
Nandadeep Residency
P51800015173 · Kurla
Ruko
Rose Garden
P51800022587 · Andheri
Ruko
Simra Residency
P51800029958 · Kurla
Ruko