BUILDER

Vikas Vilas Bhalgat

Type Firm / individualRERA projects 6Districts Pune
BUILDER THOK
Dhyaan Do
3 of 6projects with possession moved
7 moaverage extension when late
2lapsed registrations
6MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Kuber Kunjban
Pune (M Corp.)
Jul 2019Jul 2019
not moved
Kuber Imperia
Wakad · lapsed
Apr 2024Apr 2024
lapsed
Kuber Antonia
Wakad · lapsed
Feb 2025Feb 2026
12 mo
Apr 2027Apr 2027
not moved
Apr 2027Aug 2027
4 mo
Aug 2027Dec 2027
4 mo

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Kuber Kunjban
P52100001616 · Pune (M Corp.)
Ruko
Kuber Imperia
P52100016321 · Wakad
Ruko
Kuber Antonia
P52100035197 · Wakad
Ruko
Kuber Antonia C Wing
P52100053142 · Mulshi
Pakka
Kuber Antonia A Wing
P52100056209 · Mulshi
Pakka
Kuber Mudra Meadows
P52100077821 · Ambegaon
Pakka