Type Firm / individualRERA projects 9Districts Pune, Sindhudurg, Thane, Nashik, Nagpur
BUILDER THOK
Dhyaan Do
4 of 9projects with possession moved
16 moaverage extension when late
2lapsed registrations
9MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Vrundavan Park
Baramati (M Cl)
Dec 2018Dec 2018
not moved
Parvati Pride
Banda (ct) · lapsed
May 2021Nov 2024
42 mo
Dec 2023Apr 2024
4 mo
Vrundavan Park Phase 2
Baramati · lapsed
Mar 2024Mar 2024
lapsed
Ambayani Chsl
Ambarnath
Jun 2025Jun 2025
not moved
Dec 2025Dec 2026
12 mo
Dec 2025Dec 2025
not moved
Mar 2027Jul 2027
4 mo
Jun 2029Jun 2029
not moved

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Vrundavan Park
P52100006477 · Baramati (M Cl)
Ruko
Parvati Pride
P52900016208 · Banda (ct)
Ruko
Vedant Developers
P52100048105 · Hadapsar
Pakka
Vrundavan Park Phase 2
P52100029572 · Baramati
Ruko
Ambayani Chsl
P51700048169 · Ambarnath
Pakka
Vrundawan Park C Building
P52100048725 · Baramati
Dhyaan Do
Vrundawan Park Amenity Commercial
P52100048748 · Baramati
Dhyaan Do
Nilamay Apartment
P51600080854 · Nashik
Pakka
Aerocity 1
PP1190002601555 · Hingna
Pakka