BUILDER
Vascon Engineers LTD
BUILDER THOK
Ruko
3 of 12projects with possession moved
13 moaverage extension when late
2lapsed registrations
12MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Signals from filings & records
2 projects lapsed on MahaRERAMahaRERA
Registration lapsed without completion being recorded.
MahaRERA registration
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Platinum Square Phase 1
P52100001434 · Vimannagar
Vista II
P51600001313 · Nashik
Windermere Phase 1
P52100003865 · Koregaon Park
Windermere Phase 2
P52100002368 · Koregaon Park
Platinum Square Phase 2
P52100012916 · Vimannagar
Vascon Goodlife Phase A
P52100016242 · Katavi
Vascon Goodlife Phase C
P52100016293 · Katavi
Vascon Goodlife Phase B
P52100016237 · Katavi
Eco Tower Phase 2
P52100034892 · Haveli
Tower Of Ascend
P52100051705 · Haveli
Vascon Orchids
P51800078870 · Andheri
Vascon Onyx Residences
PM1180002601508 · Andheri