Type Firm / individualRERA projects 2Districts Aurangabad, Nagpur
BUILDER THOK
Ruko
2 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Udyog Varad
Devlai · lapsed
Jun 2026Oct 2026
4 mo
Varad Enclave
Nagpur (urban)
Nov 2029Mar 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Udyog Varad
P51500027010 · Devlai
Ruko
Varad Enclave
P50500080050 · Nagpur (urban)
Pakka