Vaishnavi Developers

Type Firm / individualRERA projects 9Districts Pune, Thane, Nashik
BUILDER THOK
Dhyaan Do
7 of 9projects with possession moved
4 moaverage extension when late
2lapsed registrations
9MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Bajirao Park
Haveli · lapsed
Mar 2023Sept 2023
6 mo
Vaishnavi
Haveli
Jul 2023Jul 2023
not moved
Vaishnavi Heights
Ambarnath · lapsed
Jan 2024Jan 2024
lapsed
Vaishnavi Pride
Chinchpada
Dec 2026Apr 2027
4 mo
Vaishnavi Devyani Park
Nashik (M Corp.)
Dec 2026Apr 2027
4 mo
Dec 2026Apr 2027
4 mo
Dec 2027Apr 2028
4 mo
May 2028Sept 2028
4 mo
Dec 2029Apr 2030
4 mo

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Bajirao Park
P52100023669 · Haveli
Ruko
Vaishnavi
P52100021876 · Haveli
Ruko
Vaishnavi Heights
P51700023882 · Ambarnath
Ruko
Vaishnavi Pride
P51700046405 · Chinchpada
Pakka
Vaishnavi Devyani Park
P51600045961 · Nashik (M Corp.)
Pakka
Vaishnavi Aaradhya Heights
P51600033463 · Nashik (M Corp.)
Pakka
Vaishnavi Bliss
PM1330002501540 · Kalyan
Pakka
Shree Gurudev Plaza
P52100079866 · Khed
Pakka
Vaishnavi Heaven
PR1330002502284 · Ambarnath
Pakka