Upvan Developers

Type Firm / individualRERA projects 2Districts Mumbai Suburban
BUILDER THOK
Dhyaan Do
2 of 2projects with possession moved
14 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Astrum
Borivali
Dec 2024Dec 2026
24 mo
Mar 2030Jul 2030
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Astrum
P51800029353 · Borivali
Dhyaan Do
Woodlands Reserve
PR1180002600265 · Borivali
Pakka