BUILDER

Trimurti Developers

Type Firm / individualRERA projects 14Districts Pune, Ahmednagar, Raigarh
BUILDER THOK
Ruko
8 of 14projects with possession moved
13 moaverage extension when late
5lapsed registrations
14MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Grand Icon
Ambegaon Bk
May 2019May 2019
not moved
Dec 2019Dec 2019
not moved
Trimurti Phase 3
Shrigonda · lapsed
Sept 2021Mar 2022
6 mo
Swapngandh
Haveli · lapsed
Dec 2021Dec 2021
lapsed
Shiv Park
Wagholi
Mar 2022Sept 2022
6 mo
Samruddhi Plaza
Haveli · lapsed
Sept 2022Sept 2023
12 mo
Dec 2022Dec 2022
not moved
Crystal Park
Mohammadwadi
Feb 2023Feb 2023
not moved
Shiv Krupa Residency
Panvel · lapsed
Aug 2023Aug 2024
12 mo
Shiv Hills Phase 2
Haveli · lapsed
Jun 2024Jun 2025
12 mo
Jun 2025Apr 2029
46 mo
Wisteria
Mulshi
Dec 2027Apr 2028
4 mo
The Rise
Haveli
Dec 2028Apr 2029
4 mo
Mar 2029Mar 2029
not moved

Signals from filings & records

5 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Grand Icon
P52100006202 · Ambegaon Bk
Ruko
Savitri Complex
P52100012055 · Otur
Ruko
Trimurti Phase 3
P52200018237 · Shrigonda
Ruko
Swapngandh
P52100018059 · Haveli
Ruko
Shiv Park
P52100015980 · Wagholi
Ruko
Samruddhi Plaza
P52100025915 · Haveli
Ruko
Trimurti Park
P52100018275 · Haveli
Ruko
Crystal Park
P52100019837 · Mohammadwadi
Ruko
Shiv Krupa Residency
P52000028546 · Panvel
Ruko
Shiv Hills Phase 2
P52100027023 · Haveli
Ruko
Vaishnavi Arcade Phase 2
P52100026757 · Haveli
Ruko
Wisteria
P52100046180 · Mulshi
Pakka