BUILDER

Trimity Constructions

Type Firm / individualRERA projects 4Districts Thane
BUILDER THOK
Ruko
3 of 4projects with possession moved
28 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Trimity Ashwa
Thane (M Corp.)
Dec 2017Dec 2017
not moved
Harmony
Thane (M Corp.)
Mar 2023Apr 2027
49 mo
Shri Shivanand CHS
Thane (M Corp.)
Jun 2023Aug 2024
14 mo
Dec 2024Oct 2026
22 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Trimity Ashwa
P51700007057 · Thane (M Corp.)
Ruko
Harmony
P51700022306 · Thane (M Corp.)
Ruko
Shri Shivanand CHS
P51700024183 · Thane (M Corp.)
Dhyaan Do
Asavari Co Op Hsg Soc LTD
P51700045809 · Thane
Ruko