BUILDER

Swastik Enterprises

Type Firm / individualRERA projects 8Districts Raigarh, Mumbai Suburban, Thane, Palghar, Kolhapur, Sindhudurg
BUILDER THOK
Ruko
4 of 8projects with possession moved
28 moaverage extension when late
4lapsed registrations
8MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Swastik Enterprises
Panvel · lapsed
Jun 2019Jun 2022
36 mo
Shree Shambhav Darshan
Kurla · lapsed
Dec 2021Dec 2021
lapsed
Dec 2022Dec 2022
not moved
Paramount Enclave Bldg 02
Palghar · lapsed
Mar 2023Dec 2025
33 mo
Dec 2023Jan 2027
37 mo
Swastik Plaza
Kolhapur (M Corp.) · lapsed
Aug 2024Aug 2024
lapsed
Apr 2027Aug 2027
4 mo
Dwarkanagari
Charathe
Apr 2031Apr 2031
not moved

Signals from filings & records

4 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Swastik Enterprises
P52000011118 · Panvel
Ruko
Shree Shambhav Darshan
P51800003335 · Kurla
Ruko
Vihang Apartment
P51700018895 · Bhiwandi
Ruko
Paramount Enclave Bldg 02
P99000017353 · Palghar
Ruko
Mahalaxmi Ashish D Wing
P51700020000 · Dombivli
Ruko
Swastik Plaza
P53000007948 · Kolhapur (M Corp.)
Ruko
Jai Bhavani CHS
PM1330002501515 · Ambarnath
Pakka
Dwarkanagari
P52900010891 · Charathe
Pakka