Sumer Builders

Type Firm / individualRERA projects 2Districts Mumbai City
BUILDER THOK
Ruko
1 of 2projects with possession moved
12 moaverage extension when late
2lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sumer Trinity Vertical Phase-i
Gsouth-400025 · lapsed
Jun 2023Jun 2024
12 mo
Sumer Aarambh
Ward Gsouth · lapsed
Jun 2025Jun 2025
lapsed

Signals from filings & records

2 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sumer Trinity Vertical Phase-i
P51900017371 · Gsouth-400025
Ruko
Sumer Aarambh
P51900046330 · Ward Gsouth
Ruko