BUILDER

Sugee Developers PVT LTD

Type CompanyRERA projects 9Districts Mumbai City, Mumbai Suburban
BUILDER THOK
Dhyaan Do
3 of 9projects with possession moved
20 moaverage extension when late
0lapsed registrations
9MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Trimurti
Gnorth-400028
Apr 2018Apr 2018
not moved
Govind Sadan
Gnorth-400028
Dec 2020Dec 2020
not moved
Sugee Parimal
Ward Gnorth
Dec 2023Dec 2023
not moved
Atharva
Ward Gsouth
Dec 2025Dec 2025
not moved
Indira
Gnorth-400028
Apr 2026Apr 2026
not moved
Sea Krest
Ward Gsouth
Dec 2027Apr 2030
28 mo
Nov 2028Mar 2029
4 mo
Dec 2029Apr 2032
28 mo
Sugee Vrundavan
Ward Gnorth
Dec 2029Dec 2029
not moved

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Trimurti
P51900004360 · Gnorth-400028
Ruko
Govind Sadan
P51900000834 · Gnorth-400028
Pakka
Sugee Parimal
P51900023350 · Ward Gnorth
Ruko
Atharva
P51900027433 · Ward Gsouth
Dhyaan Do
Indira
P51900048976 · Gnorth-400028
Dhyaan Do
Sea Krest
P51900051903 · Ward Gsouth
Ruko
Shree Krishnakunj
PR1170002501200 · Ward Gnorth
Pakka
Sugee Vaayu
P51800053945 · Kurla
Ruko
Sugee Vrundavan
PR1170002601623 · Ward Gnorth
Pakka