BUILDER

Sterling Developers

Type Firm / individualRERA projects 2Districts Satara
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sterling Residency
Khandala · lapsed
Dec 2025Dec 2025
lapsed
Sept 2027Jan 2028
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sterling Residency
P52700045591 · Khandala
Ruko
Sterling Residency Building C5 And C6
PR1301012500292 · Khandala
Pakka