2 of 4projects with possession moved
16 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Indraprasth Wing C
Mira-bhayandar (M Corp.)
Sept 2020Sept 2020
not moved
Rental Building A-1 R2
Mira-bhayandar (M Corp.)
Sept 2020Dec 2019
not moved
Indra Neel
Mira-bhayandar (M Corp.)
Jun 2026Sept 2027
15 mo
Opulence
Mira-bhayandar (M Corp.)
Dec 2027Apr 2029
16 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Indraprasth Wing C
P51700002491 · Mira-bhayandar (M Corp.)
Ruko
Rental Building A-1 R2
P51700004747 · Mira-bhayandar (M Corp.)
Pakka
Indra Neel
P51700027465 · Mira-bhayandar (M Corp.)
Dhyaan Do
Opulence
P51700031137 · Mira-bhayandar (M Corp.)
Dhyaan Do