Sol Developers

Type Firm / individualRERA projects 4Districts Pune
BUILDER THOK
Dhyaan Do
2 of 4projects with possession moved
23 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
The Address - 1
Pimpri Chinchawad (M Corp.)
Jun 2019Jun 2019
not moved
The Address - 2
Pimpri Chinchawad (M Corp.)
Jun 2020Jun 2022
24 mo
The Address Phase-3
Pimpri Chinchawad (M Corp.)
Nov 2023Nov 2023
not moved
The Address Phase-4
Pimpri Chinchawad (M Corp.)
Jun 2026Apr 2028
22 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

The Address - 1
P52100007674 · Pimpri Chinchawad (M Corp.)
Pakka
The Address - 2
P52100007886 · Pimpri Chinchawad (M Corp.)
Ruko
The Address Phase-3
P52100020839 · Pimpri Chinchawad (M Corp.)
Pakka
The Address Phase-4
P52100032678 · Pimpri Chinchawad (M Corp.)
Dhyaan Do