BUILDER

Skyline Landmark Projects Private Limited

Type CompanyRERA projects 2Districts Mumbai Suburban
BUILDER THOK
Dhyaan Do
0 of 2projects with possession moved
0 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Vijayagar
Borivali
Dec 2022Dec 2022
not moved
Ashwin
Borivali · lapsed
Sept 2025Sept 2025
lapsed

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Vijayagar
P51800029943 · Borivali
Pakka
Ashwin
P51800056201 · Borivali
Ruko