2 of 2projects with possession moved
22 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2023Apr 2027
40 mo
Dec 2026Apr 2027
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Skicity Phase 1
P51800007336 · Kurla
Ruko
Skicity Symphony
P51800056359 · Mumbai
Pakka