BUILDER

Siraj Karim Pathan

Type Firm / individualRERA projects 2Districts Ratnagiri
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Merc Apartment
Ratnagiri · lapsed
Dec 2025Dec 2025
lapsed
Dec 2028Apr 2029
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Merc Apartment
P52800029383 · Ratnagiri
Ruko
Haji Umar Complex
P52800080997 · Ratnagiri
Pakka