BUILDER

Shreenath Developers

Type Firm / individualRERA projects 6Districts Wardha, Thane, Pune, Mumbai Suburban
BUILDER THOK
Ruko
4 of 6projects with possession moved
27 moaverage extension when late
3lapsed registrations
6MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Shree Nath Residency
Palakwadi (wardha)
Dec 2018Dec 2018
not moved
Royal Castle
Ambarnath(m Cl) · lapsed
Nov 2020Mar 2024
40 mo
Dec 2023May 2027
41 mo
Dec 2024Oct 2026
22 mo
Aai Satidevi Paradise
Kurla · lapsed
Mar 2026Sept 2026
6 mo
Mar 2027Mar 2027
not moved

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shree Nath Residency
P50400006072 · Palakwadi (wardha)
Ruko
Royal Castle
P51700010834 · Ambarnath(m Cl)
Ruko
Royal Castle Phase 2
P51700021992 · Ambarnath (R)
Ruko
Indrayani Riverview Residency
P52100051634 · Haveli
Ruko
Aai Satidevi Paradise
P51800054925 · Kurla
Ruko
Shilpa Resedency
P51700034735 · Ambarnath
Pakka