BUILDER

Shree Samarth Enterprises

Type Firm / individualRERA projects 4Districts Thane
BUILDER THOK
Pakka
4 of 4projects with possession moved
7 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2025Apr 2027
16 mo
Mar 2028Jul 2028
4 mo
Deepsamay CHS
Ambarnath
Jun 2028Oct 2028
4 mo
Sept 2028Jan 2029
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Om Dutta Deep Co. Op Hsg
P51700054486 · Ambarnath
Dhyaan Do
Raj Vaibhav Park
PM1330002600949 · Kalyan
Pakka
Deepsamay CHS
P51700080595 · Ambarnath
Pakka
Swaraswati Heights
P51700055115 · Ambarnath
Pakka