BUILDER

Shree Sainath Land & Development (india) Private Limited

Type CompanyRERA projects 3Districts Nashik
BUILDER THOK
Ruko
1 of 3projects with possession moved
24 moaverage extension when late
3lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Hari Nakshatra Phase I
Deolaligaon · lapsed
Mar 2022Mar 2024
24 mo
Destination One
Deolaligaon · lapsed
Mar 2023Mar 2023
lapsed
Hari Nakshatra Phase II
Deolaligaon · lapsed
Sept 2023Sept 2023
lapsed

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Hari Nakshatra Phase I
P51600012149 · Deolaligaon
Ruko
Destination One
P51600006359 · Deolaligaon
Ruko
Hari Nakshatra Phase II
P51600006285 · Deolaligaon
Ruko