Shree Sai Shraddha Associates

Type Firm / individualRERA projects 2Districts Mumbai Suburban
BUILDER THOK
Ruko
2 of 2projects with possession moved
74 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mar 2018Dec 2026
105 mo
Shree Sambhav Darshan CHS
Borivali · lapsed
Jun 2022Dec 2025
42 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements