Shree Krishna Enterprises

Type Firm / individualRERA projects 7Districts Thane, Ratnagiri, Raigarh
BUILDER THOK
Dhyaan Do
4 of 7projects with possession moved
6 moaverage extension when late
1lapsed registrations
7MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mohan Ritteka
Ulhasnagar (M Corp.)
Mar 2018Mar 2019
12 mo
Dec 2021Dec 2021
not moved
Madhu Villa
Kalyan-dombivali (M Corp.) · lapsed
Dec 2022Dec 2022
lapsed
May 2023May 2023
not moved
Dec 2027Apr 2028
4 mo
Dec 2027Apr 2028
4 mo
Dec 2032Apr 2033
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Mohan Ritteka
P51700004103 · Ulhasnagar (M Corp.)
Ruko
Shreeji Gulmohar - Phase 1
P52800015084 · Jalgaon
Ruko
Madhu Villa
P51700027091 · Kalyan-dombivali (M Corp.)
Ruko
Shreeji Gulmohar - Phase 2
P52800017055 · Dapoli
Pakka
Kanha Heights
P52000077222 · Panvel
Pakka
Krishna Crystal
P52000055038 · Panvel
Pakka
Galaxy Vrundavan
P52000080710 · Karjat
Pakka