BUILDER

Shree Adeshwar Buildcom

Type Firm / individualRERA projects 2Districts Palghar
BUILDER THOK
Ruko
1 of 2projects with possession moved
18 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2020Jun 2022
18 mo
Dec 2022Dec 2022
not moved

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Aadeshwar-2
P99000011704 · Umroli
Ruko
Vajreshwari Apartment
P99000017638 · Umroli
Ruko