Shiv Corporation

Type Firm / individualRERA projects 4Districts Thane
BUILDER THOK
Dhyaan Do
2 of 4projects with possession moved
4 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Shiv Samarth
Badlapur (M Cl)
Sept 2020Sept 2020
not moved
Shiv Paradise
Badlapur (M Cl)
Dec 2025Dec 2025
not moved
Dec 2026Apr 2027
4 mo
Shiv Elysium
Ambarnath
Dec 2028Apr 2029
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shiv Samarth
P51700016324 · Badlapur (M Cl)
Ruko
Shiv Paradise
P51700046607 · Badlapur (M Cl)
Dhyaan Do
Shiv Paradise Wing C
P51700055322 · Ambarnath
Pakka
Shiv Elysium
PR1330002502526 · Ambarnath
Pakka