Shibam Associates

Type Firm / individualRERA projects 4Districts Raigarh
BUILDER THOK
Ruko
2 of 4projects with possession moved
26 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mar 2019Mar 2019
not moved
Nov 2019Nov 2020
12 mo
May 2022May 2022
not moved
Cluster A
Karjat
Dec 2023Apr 2027
40 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.