BUILDER

Shalini Shivaji Pawar

Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Ruko
2 of 2projects with possession moved
85 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Shiv Shahi Complex
Narayangaon · lapsed
Jun 2019Dec 2025
78 mo
Dec 2022Jul 2030
91 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shiv Shahi Complex
P51700015735 · Narayangaon
Ruko
Shiv Shahi Complex Phase II
P51700017015 · Murbad
Ruko