BUILDER

Shakti Builders And Developers

Type Firm / individualRERA projects 2Districts Nagpur
BUILDER THOK
Dhyaan Do
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Galaxy Park
Kamptee · lapsed
Jun 2025Jun 2025
lapsed
Jun 2029Oct 2029
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Galaxy Park
P50500052403 · Kamptee
Ruko
Galaxy Park 4
PR1190002601314 · Kamptee
Pakka