Type Firm / individualRERA projects 2Districts Thane
BUILDER THOK
Ruko
1 of 2projects with possession moved
4 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2022Dec 2022
not moved
Dec 2030Apr 2031
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shree Siddhivinayak Park Wing A1 And A2
P51700016720 · Murbad
Ruko
Shree Siddhivinayak Park B1 And B2
P51700050066 · Murbad
Pakka