4 of 8projects with possession moved
10 moaverage extension when late
3lapsed registrations
8MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sai Icon
Ambivali Tarf Chon · lapsed
Dec 2023Dec 2023
lapsed
Dwarkanath Heights
Kalyan · lapsed
Mar 2024Dec 2025
21 mo
Sai Darshan
Pune (M Corp.)
Mar 2024Mar 2024
not moved
Sai Darshan Phase II
Pune (M Corp.)
Dec 2025Dec 2026
12 mo
Meriton Towers
Haveli · lapsed
Feb 2026Feb 2026
lapsed
Mar 2027Mar 2027
not moved
Dec 2029Apr 2030
4 mo
Jun 2030Oct 2030
4 mo

Signals from filings & records

3 projects lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sai Icon
P51700020449 · Ambivali Tarf Chon
Ruko
Dwarkanath Heights
P51700023331 · Kalyan
Ruko
Sai Darshan
P52100026605 · Pune (M Corp.)
Ruko
Sai Darshan Phase II
P52100050010 · Pune (M Corp.)
Dhyaan Do
Meriton Towers
P52100027260 · Haveli
Ruko
Shiv Heights
P51600051591 · Nashik
Pakka
Sai Shraddha Phase II
P52000056228 · Roha
Pakka
Sai Icon Type B
PR1331012500948 · Kalyan
Ruko