BUILDER

Sai Sakshi Developers

Type Firm / individualRERA projects 2Districts Nashik, Thane
BUILDER THOK
Ruko
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Jun 2024Jun 2024
not moved
Sai Aashiyana - II
Tisgaon · lapsed
Jun 2026Oct 2026
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sai Vishva
P51600028910 · Nashik
Ruko
Sai Aashiyana - II
P51700026248 · Tisgaon
Ruko