BUILDER

Sagar Sohanlal Bhandari

Type Firm / individualRERA projects 2Districts Nashik
BUILDER THOK
Ruko
1 of 2projects with possession moved
4 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sohan City Phase 2
Niphad · lapsed
Dec 2025Dec 2025
lapsed
Dec 2026Apr 2027
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sohan City Phase 2
P51600031995 · Niphad
Ruko
Sohan City Phase 2 Lasalgaon
P51600053297 · Niphad
Pakka