BUILDER

S V Enterprises

Type Firm / individualRERA projects 3Districts Raigarh, Nashik
BUILDER THOK
Ruko
0 of 3projects with possession moved
0 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Mar 2019Mar 2019
not moved
Hill Woods
Deolali (cb) · lapsed
Jan 2023Jan 2023
lapsed
Oak Woods
Sansari
Nov 2024Nov 2024
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Shireen Plaza
P52000016254 · Neral
Pakka
Hill Woods
P51600009809 · Deolali (cb)
Ruko
Oak Woods
P51600023506 · Sansari
Ruko