BUILDER

Renaissance Spaces

Type Firm / individualRERA projects 3Districts Mumbai Suburban, Mumbai City
BUILDER THOK
Dhyaan Do
1 of 3projects with possession moved
4 moaverage extension when late
1lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2023Dec 2023
lapsed
Dec 2023Dec 2023
not moved
The Baya Sunrise
Ward Fsouth
Dec 2029Apr 2030
4 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

7th Floor - C Wing - The Baya Goldspot
P51800008945 · Andheri
Ruko
Floors 8 And 9 - The Baya Goldspot
P51800020972 · Andheri
Pakka
The Baya Sunrise
P51900055576 · Ward Fsouth
Pakka