BUILDER
Reliable Constructions
BUILDER THOK
Ruko
3 of 4projects with possession moved
23 moaverage extension when late
1lapsed registrations
4MahaRERA projects
Delivery track record
Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Signals from filings & records
1 project lapsed on MahaRERAMahaRERA
Registration lapsed without completion being recorded.
MahaRERA registration
No approved insolvency matchIBBI
No IBBI announcement has been matched to this builder after review.
IBBI public announcements
Projects
Vasundhara CHS LTD - Phase II - A And B Wing
P51800005777 · Borivali
Laxmi Nagar
P51800010918 · Borivali
Shastri Nagar Prabhat Chsl Phase II A And B Wing
P51800033876 · Borivali
Anandi Malhar
PR1260002501174 · Ambegaon