BUILDER

Raman Babaso Khamkar

Type Firm / individualRERA projects 2Districts Pune, Ahmednagar
BUILDER THOK
Ruko
1 of 2projects with possession moved
60 moaverage extension when late
1lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Swaraj
Patas
Jan 2018Jan 2018
not moved
Vrundavan City
Karjat · lapsed
Dec 2019Dec 2024
60 mo

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Swaraj
P52100007657 · Patas
Ruko
Vrundavan City
P52200018783 · Karjat
Ruko