2 of 4projects with possession moved
12 moaverage extension when late
1lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
May 2019Nov 2020
18 mo
Dec 2019Dec 2019
not moved
Jun 2022Dec 2022
6 mo
Mar 2023Mar 2023
not moved

Signals from filings & records

1 project lapsed on MahaRERAMahaRERA

Registration lapsed without completion being recorded.

MahaRERA registration
No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Akshay City A And B Building
P52100002357 · Kanhe
Ruko
Akshay Residency
P52100005552 · Wakad
Ruko
Akshay Residency A Building
P52100029532 · Mulshi
Ruko
Akshay Srushti
P52100015477 · Charholi