BUILDER

Radha Madhav Developers

Type Firm / individualRERA projects 3Districts Nagpur
BUILDER THOK
Dhyaan Do
1 of 3projects with possession moved
4 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Gokul
Wagdara (536084)
Dec 2022Dec 2022
not moved
Dec 2027Dec 2027
not moved
Dec 2028Apr 2029
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements