Pranav Buildcon Pvt. Ltd.

Type CompanyRERA projects 3Districts Sangli
BUILDER THOK
Ruko
1 of 3projects with possession moved
24 moaverage extension when late
0lapsed registrations
3MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Nishigandh Apratments
Sangli Miraj Kupwad (M Corp.)
Sept 2018Sept 2018
not moved
Sainandan Enclave
Sangli Miraj Kupwad (M Corp.)
Mar 2019Mar 2019
not moved
Daffodils Apartment
Sangli Miraj Kupwad (M Corp.)
May 2025May 2027
24 mo