BUILDER

Pinnacle Corporation

Type Firm / individualRERA projects 4Districts Thane
BUILDER THOK
Dhyaan Do
1 of 4projects with possession moved
4 moaverage extension when late
0lapsed registrations
4MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Dec 2023Dec 2023
not moved
Sai Tirth Phase II
Badlapur (M Cl)
Mar 2025Mar 2025
not moved
Sai World
Badlapur (M Cl)
Mar 2026Mar 2026
not moved
Sai Universe
Ambarnath
Dec 2029Apr 2030
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sai Tirth Phase I
P51700020430 · Ambarnath
Ruko
Sai Tirth Phase II
P51700034566 · Badlapur (M Cl)
Pakka
Sai World
P51700034155 · Badlapur (M Cl)
Dhyaan Do
Sai Universe
PR1330002601334 · Ambarnath
Pakka