BUILDER

Pandit Nanabhau Molak

Type Firm / individualRERA projects 2Districts Pune
BUILDER THOK
Pakka
1 of 2projects with possession moved
4 moaverage extension when late
0lapsed registrations
2MahaRERA projects

Delivery track record

Possession date first declared vs latest on MahaRERA
PROJECTPROMISEDLATESTMOVED BY
Sept 2020Nov 2019
not moved
Mar 2030Jul 2030
4 mo

Signals from filings & records

No approved insolvency matchIBBI

No IBBI announcement has been matched to this builder after review.

IBBI public announcements

Projects

Sayali Complex
P52100008283 · Dehu
Pakka
Vighnaharta
P52100080468 · Haveli
Pakka